TxDOT I-30 EXPANSION PROJECT UPDATES
(Click the image below to go to their website.)

 

PROJECT DETAILS/OVERVIEW

The I-30 expansion project will widen I-30 from Bass Pro Dr. to the Hunt County Line and add continuous frontage roads, including across Lake Ray Hubbard. The current configuration is inadequate to handle traffic congestion and population growth, and results in bottlenecks and road closures when there is an incident on the lake bridge. Adding separate frontage road bridges and expanding the mainlanes means traffic can continue to cross the lake if an incident has closed or limited general purpose lanes.

 

TxDOT VIDEO
Project update: I-30 expansion in Rockwall County

 

PROJECT TIMELINE

Segment 1:

  • ƒLimits: Bass Pro Dr. to Dalrock Rd.
  • ƒConstruction Began: July 2021
  • ƒEst. Cost: $142 million
  • ƒWork: Will construct from 0 to 6 lane frontage roads, Bayside Dr. bridge & ramp modifications, as well as reconstruct the Dalrock Rd. interchange
  • ƒEst. Completion: Aug. 2024
  • ƒContractor: Sema Construction, Inc.

 

Fall 2022 Segment 1 Updates:

  • ƒContinue construction of the eastbound frontage road.
  • ƒBegin pouring the bridge deck for the eastbound mainlane widening bridge.
  • ƒThe Dalrock Flyover substructure is nearing completion.
  • ƒMobilizing cranes and drilling units to the westbound frontage road to begin drill shafts in the water.
  • ƒBuilding retaining and sound walls
  • ƒReconstruction of Bayside Drive
  • ƒContinue work on Dalrock underpass

 

Segment 2 (Letting in Fall 2022):

  • ƒLimits: Dalrock Rd. to SH 205
  • ƒCSJs: 0009-12-215 & 0009-12-220*
    (Dalrock Rd. to east of Horizon Dr.)
  • ƒEst. Construction: To begin late 2022
  • ƒEst. Cost: $89 million (CSJ 009-12-215), $172 million* (CSJ 009-12-220)
  • ƒWork: Add shoulder, reconstruct, and widen existing 6 mainlanes to 8, construct 0 to 6 lane frontage roads over the lake, reconstruct existing frontage roads, ramp modifications

 

Segment 3 (Letting in Fall 2022):

  • ƒLimits: SH 205 to Hunt Co. Line
  • ƒCSJ: 0009-12-219
  • ƒEst. Construction: To begin late 2022
  • ƒEst. Cost: $289 million
  • ƒWork: Reconstruct and widen 4 mainlanes to 6, reconstruct and widen 4 frontage roads to 4/6, construct new & reconstruct existing interchanges, ramp modifications